24" and 30" Linestop on RCP Water Main under 60 psi No By-pass
- Details
IFT Featured California Job: 24" and 30" Linestop on RCP Water Main under 60 psi No By-pass - 5.0 out of
5
based on
5 reviews
24" and 30" Linestop on RCP Water Main under 60 PSI No By-pass

Job Status: Successful and Completed
Job Date: September 25, 2017
JOB LOCATION: Whittier, CA.
PROJECT: Torrance Medical Center
Job Specifics: Whittier Line stop Project
1 – Mobilization – Prep / Travel to job site
Item l - 30” Linestop® on 30” RCP Water Main - under 60 psi – No By-pass
2 - Mobilization – Prep / Travels to Site
1 - 30” x 24” Linestop® Fitting for RCP waterline (ANSI 150 Fitting)
(JCM 442 Fusion Epoxy Coated with Stainless Steel Bolts & Double Gasket)
1 - Install & Pressure Test Linestop® Fitting, Hottap Pipe, and install Linestop®
1 - 30” Linestop® held for up to 3 Days while you perform pipeline modifications
1 - Removal of Linestop and installation of Completion Plug with Blind Flange
1 - Blow-off assembly as required
Item Il - 24” Linestop® on 24” RCP Water Main - under 60 psi – No By-pass
2 - Mobilization – Prep / Travels to Site
1 - 24” x 16” Linestop® Fitting for RCP waterline (ANSI 150 Fitting)
(JCM 442 Fusion Epoxy Coated with Stainless Steel Bolts & Double Gasket)
1 - Install & Pressure Test Linestop® Fitting, Hottap Pipe, and install Linestop®
1 - 24” Linestop® held for up to 3 Days while you perform pipeline modifications
1 - Removal of Linestop and installation
Job Date: September 25, 2017
JOB LOCATION: Whittier, CA.
PROJECT: Torrance Medical Center
Job Specifics: Whittier Line stop Project
1 – Mobilization – Prep / Travel to job site
Item l - 30” Linestop® on 30” RCP Water Main - under 60 psi – No By-pass
2 - Mobilization – Prep / Travels to Site
1 - 30” x 24” Linestop® Fitting for RCP waterline (ANSI 150 Fitting)
(JCM 442 Fusion Epoxy Coated with Stainless Steel Bolts & Double Gasket)
1 - Install & Pressure Test Linestop® Fitting, Hottap Pipe, and install Linestop®
1 - 30” Linestop® held for up to 3 Days while you perform pipeline modifications
1 - Removal of Linestop and installation of Completion Plug with Blind Flange
1 - Blow-off assembly as required
Item Il - 24” Linestop® on 24” RCP Water Main - under 60 psi – No By-pass
2 - Mobilization – Prep / Travels to Site
1 - 24” x 16” Linestop® Fitting for RCP waterline (ANSI 150 Fitting)
(JCM 442 Fusion Epoxy Coated with Stainless Steel Bolts & Double Gasket)
1 - Install & Pressure Test Linestop® Fitting, Hottap Pipe, and install Linestop®
1 - 24” Linestop® held for up to 3 Days while you perform pipeline modifications
1 - Removal of Linestop and installation
OR Call
Office hours 7:30 – 5:00 Central time
Nationwide: 1-800-221-3332
Emergency Services Available .