10" Linestop on DIP-CI-PVC Water Main below ground under 100 psi Washington with Completion Plug

10inch Linestop on DIP-CI-PVC Water Main below ground under 100 psi Washington with Completion Plug

Job Status: Successful and Completed
Job Date: November 3, 2017
JOB LOCATION:  Seattle, WA.
PROJECT: 10" Linestop
Job Specifics:
1 – Mobilization - Prep / Travel to site: 

Item I: 10” Linestop® on DIP/CI /PVC Water Main below ground under 100 psi
1 – 10” Linestop fitting - Epoxy Coated w/ SS nuts and Bolts
1 – Installation of Fittings and temporary valve with leak test.
1 – Hot Tap to allow for Linestop entry
1 – Insertion of 10” Linestop – held for up to 8 hours while Contractor performs Pipeline modifications
1 – Removal of Linestop, installation of Completion Plug and Blind Flange.
Installation of Blow-off assemblies as required for removal of Linestop